Summary of national steel plant production reduction and maintenance information

  In recent days, the market price has been dropping rapidly and the production profit of steel mills has been squeezed continuously. The number of steel mills with maintenance and production reduction under the state of loss has gradually increased.

  [summary of blast furnace maintenance information]

  Ping'an iron and Steel Co., Ltd.: it is planned to overhaul Anyuan 1\ (450m3) and 4\\\ (1080m3) blast furnaces from June 22, and the completion time of overhaul is to be determined.

  Shaanxi iron and Steel Group: on the evening of June 20, a 1800m3 blast furnace in the plant was overhauled, which is expected to last 10-15 days. The daily average molten iron output is about 6000 tons. One strip rolling line and one thread rolling line in the synchronous plant are shut down for maintenance; One sintering line was shut down for maintenance for 7 days.

  Shanxi Jinnan iron and Steel Co., Ltd.: originally planned to build an 1860m building in the plant on the evening of June 20 ³ The blast furnace has been shut down for maintenance. Now, two 550m blast furnaces in Xingyuan are actually repaired ³ Blast furnace, Yufeng No.1 450m ³ Blast furnace, henglue, 450m ³ The blast furnace will be shut down for maintenance for about 30 days, and the daily molten iron output will be about 7000 tons.

  Dadonghai, Fujian: June 20 to 1260m ³ The blast furnace will be shut down for overhaul, and the time for resumption of production is to be determined. It is estimated that the overhaul will affect the average daily output of about 2000 tons.

  Wuhu Fuxin: on June 20, a 680m building was shut down for maintenance ³ The blast furnace is expected to be overhauled for 10 days, with an average daily output of about 25000 tons.

  Jilin gangang: on June 18, a 450m building was overhauled ³ The blast furnace is expected to be overhauled for 30 days, affecting the molten iron production of about 60000 tons in total.

  Fushun new iron and Steel Co., Ltd.: from June 10, a 580m building in the plant will be built ³ The blast furnace will be repaired annually for about 30 days. It is estimated that the daily output of molten iron will be reduced by about 1500 tons, affecting the output of molten iron by about 45000 tons.

  Tangshan and surrounding steel plants: since June 15, a total of 7 blast furnaces have been overhauled, with an overhaul volume of 9210m ³, The daily average hot metal production capacity is 22800 tons; From the end of June to July, a total of 10 blast furnaces of 8 steel enterprises in Tangshan and its surrounding areas are planned to be overhauled and reduced in production, with a total overhaul volume of 13460m ³, The daily average hot metal output is about 33700 tons (including the capacity of 4 blast furnaces to replace and eliminate the capacity).

  Shanxi: from June 16 to 21, a total of 4 new blast furnaces were overhauled in Shanxi, affecting about 12800 tons of iron water per day.

  Hebei: from June 17 to 20, a total of 6 new blast furnaces were overhauled in Hebei, affecting about 22500 tons of iron water per day.

  [summary of electric arc furnace / converter maintenance information]

  Ping'an iron and steel: it is planned to overhaul Anyuan converter from June 22, and the completion time of overhaul is to be determined.

  Zhejiang Lishui Huahong: it is planned to start maintenance on June 19, with a planned maintenance period of 15 days, affecting the average daily output of 5000 tons.

  Dayi base of Chengshi (plant 512): due to the shortage of raw materials, an electric furnace will be shut down on June 3, 2022, the daily output will be reduced by 3500 tons, and the time to resume normal production will be determined.

  Chongqing Iron and steel: on June 8, 1\s converter and continuous caster were overhauled. The overhaul time is expected to be 20-23 days. The daily average output of hot rolled coil is about 7500 tons, a total of about 150000 tons.

  [summary of rolling stock maintenance information]

  Ping'an iron and Steel Co., Ltd.: it is planned to overhaul Anyuan high rod heating furnace and rolling line from June 22, which is expected to affect the output of building steel by 5000 tons / day, and the completion time of overhaul is to be determined.

  Zhangjiagang Huawei special sheet: a medium plate line is planned to be shut down for maintenance from June 20 to June 25, which is expected to affect the total output of 10000 tons.

  Zhejiang Guangxin: the maintenance started on June 15, and it is planned to be maintained for 7 days, affecting the average daily output of building steel of 0700 tons.

  Zhejiang Huacheng: the overhaul started on June 10 and is planned to last for 15 days, affecting the daily average output of 1400 tons of construction steel.

  Zhejiang Kaisheng: the overhaul started on June 28, and it is planned to be overhauled for 31 days, affecting the average daily output of building steel of 0700 tons.

  Zhejiang Hengxin: the overhaul started on June 18 and is planned to last for 7 days, affecting the average daily output of building steel of 0700 tons.

  Zhejiang Huaxing: the maintenance started on June 20, and the time of resumption of production is to be determined, affecting the average daily output of building steel products of 10000 tons.

  Xinxing cast pipe (Wu'an): one bar rolling line will be overhauled for 10 days from June 20 to June 30, which is expected to affect the round steel output of 30000 tons.

  Masteel: the 2250mm Hot rolled coil production line will be shut down for maintenance for 10 days from June 28, 2022. The daily average output of hot rolled coil will be 12100 tons and the total output will be 121000 tons.

  Fushun new iron and Steel Co., Ltd.: one wire rod rolling line has been shut down for maintenance since June 5, and the time for resumption of production is to be determined. The daily output of winding line has been reduced by about 25000 tons.

  Fushun new iron and Steel Co., Ltd.: the new bar has been shut down for maintenance since June 17. It is estimated that the maintenance will take 10 days, and the daily output of rebar will be reduced by about 3000 tons.

  Jinhong Iron & Steel Co., Ltd.: it is expected that the whole plant will be shut down for maintenance from June 5 to June 20, which is expected to affect the output of about 45000 tons.